Case Study

The gables

location
watford
Sector
housing
Completion date
20.12.2023

Additional Information

material laid

SMA base, binder and AC6 wearing course in gray

Project Brief

Taydal were approached by Hawksmoor regarding some work that needed completing based in Watford. The job entailed groundworks as well as tarmac installation and involved laying footpaths throughout a residential estate. The work had to be completed before Christmas, which meant we had to squeeze it in our schedule before the end of the year.

The work we were asked to carry out involved removals of the original paving blocks, this was approximately 527 square meters. Following this, we excavated a trench for the pathways and installed 220 square meters of PCC edgings to create the footpaths. Before we could proceed with laying tarmac, we had to ensure the subbase was suitable and lay weed membrane.

The material we laid to create these pathways included 527 square meters of SMA base and binder, this was followed by a mix of AC6 wearing course in grey and red chips to create a fun effect throughout the footpaths. The work took our teams 2 days, leaving Hawksmoor and their client extremely happy with the work carried out.