DBM base course and wearing course
A.W Hardy provides expert construction services, based in East Anglia. They have been working with Tay-Dal Surfacing for many years and recently reached out to award us an install within St Christopher’s School, which is a SEN specialist school based in Leigh on Sea.
The work awarded to us involved installing new footpaths to various areas within the school grounds. The total area of these equalled 184 square meters, we had one day to complete the install. The work was completed whilst the children were within the premises, therefor we had to ensure our health and safety was top priority.
In order to complete this work, we closed off the entire area with orange barriers to ensure safety of all workers and pedestrians. We then installed 184 square meters of DBM base course and wearing course within the footpaths, ensuring it was completed to a top standard before reopening to the school.