Case Study

poppy way

location
norwich, norfolk
client
tarmac
Sector
local government
DATE COMPLETED
23.05.2025

Additional Information

material laid

10mm SMA wearing course and AC20 base course

Project Brief

Taydal had the absolute pleasure of working alongside Tarmac once again, this time we had a 5 night install over 3 roads in Norwich. Poppy Way, Broadlands Way and Wroxham Road.

The total area we had to resurface was 612 square meters. This is a smaller install, however, as the install was based on a main road, we were only allowed to install overnight for a few hours at a time. This is why this job was booked in across five nights.

 

The material chosen for this job was a AC20 base course, which was laid in various depths across the whole area. Followed by a 10mm SMA wearing course to top. We installed this on time and had the road reopened as scheduled.