Case Study

Copper Beach, Hollesley

Location
Copper Beech, Hollesley
Our Client
Opus
Sector
Housing Sector
Completion Date
18th November 2022

Additional Information

Material laid

20mm Open Graded Binder course and 10mm Ulticolour Porous Surf Buff Quartzite

How many m2?

668m2

How many days?

2

Project Brief

We were approached by Opus to carry out an install of 10mm open graded buff quartzite in Copper Beech, Hollesley, which is a beautiful housing close located in the countryside of Hollesley.

We were challenged with installing Ulticolour porous buff quartzite material on the road through the close. The buff colour of the tarmac really stands out and sets the architecture of the houses off.

Completing the job took 2 days, our teams worked hard to get this completed within our allocated deadline. Whist dealing with the heavy rains that arrived just as work began on this site, it caused our team valuable time, but our teams managed to get the jobs completed to the high standard Taydal clients expect, within the allotted time as promised.