DBM base course, DBM wearing course
Patrick Doyle Ltd are a long term client of Taydal’s, having worked with them since we opened back in 2000. They are firm friends with our managing director and regularly offer us work within the Equine industry.
The most recent work they asked us to undertake was based within the Newmarket Tattersalls on the Blue Diamond Stud. The work we had it was small, involving resurfacing a riding path within the stud. The area of this was approximately 130 square meters.
Due to the restraints of time allowed on site, this install took 2 days for our team to complete. We began with a DBM base course and completed the following day with a DBM wearing course, ready for the stud to be used to its fullest capabilities.