Case Study

Beaulieu park station

location
boreham, chelmsford
Sector
rail
CLIENT
kilnbridge construction services ltd

Additional Information

material laid

DBM base and wearing course

Project Brief

Kilnbridge recently contacted Taydal regarding some large works they needed undertaken based at the brand-new Beaulieu Park Station in Borham, Chelmsford. Beaulieu Park Station is the first new railway station built on the Great Eastern Mainline in 100 years and has been granted £281 million to complete the works.

The work we’ve been asked to undertake includes surfacing 6 new train platforms within the main station. As this is a newly built area, we had to wait until the platforms were built and ready before we could complete our work. While we were waiting for a start date for our work, we were informed of delays due to unforeseen circumstances, this meant we were delayed a further few months to begin work.

Due to this being a newly working train station, there were many health and safety risks that we had to ensure we made suitable accommodations for. This included partial and full closures of the train station dependent on the day, time and where we were working. To do this we liaised directly with Kilnbridge to ensure the closures were set up prior to our arrival to ensure we could start and finish work on site as quickly as possible.

 

As of now, some of our work is still outstanding with only 2 of the 6 platforms completed, this will mean ongoing work for our teams. Overall, we will be laying approximately 5000 square meters across the 6 platforms. The material chosen for the platforms is a DBM basecourse as well as DBM wearing course, which is suitable for everyday pedestrian traffic.