DBM road base, HRA base course, HRA wearing course and chips
10,515 m2
Our friends at Howard Construction contacted us regarding some work they had out for tender at Wolsey Grange. The new site, based off the A140 in Ipswich, is slowly becoming one of the biggest new build estates in Ipswich.
The job entailed laying a new road to extend the site so they could continue to build the houses surrounding. The road had to go down first to allow easy access for all vehicles coming in and out. The tight deadline meant we had to work quickly, laying 4000 m2 of HRA Road base, as well has 3400m2 of HRA base course and 2800m2 of HRA wearing course and chips.
The delivery of our work had to be carefully managed due to the time schedules of completing opposing works. Our teams worked quickly and efficiently, ensuring we were always working within the site’s health and safety parameters of Taylor Wimpey. The works were completed within time, leading to a very healthy relationship with Howards Construction and further works being carried out within Wolsey Grange.